IF ALL TIE LINES were of ample capacity and stations under automatic control were well distributed geographically, there would be no need for tie line control except where required by contract interchange schedules. With the large scale advent of system interconnections and the necessity for more efficient operation, the tendency is to use frequency control biased by tie line load rather than frequency control only.