Efficient testing of substation panels
Author :
Ironside, K. ; Kibart, Bill
Volume :
15
Issue :
5
fYear :
2001
Firstpage :
233
Lastpage :
238
Abstract :
The task of testing protection devices and control panels used in major projects has been exacerbated by increasing complexity and the extra functionality that they provide. The use of modern automated test equipment can address this added complexity and, at the same time, speed up the whole process. An example of where this approach has been very beneficial to the contractor was associated with the undersea 90 kV links between England and the Isle of Man. The authors describe the project. Automatic tap change control, system frequency, synchronisation, and protection panels are discussed.
Keywords :
automatic test equipment; power system control; power system protection; substations; synchronisation; 90 kV; England to Isle of Man link; automated test equipment; automatic tap change control; control panels testing; protection devices testing; protection panels; substation panels testing; synchronisation; system frequency;
fLanguage :
English
Journal_Title :
Power Engineering Journal
Publisher :
iet
ISSN :
0950-3366
Type :
jour
DOI :
10.1049/pe:20010505
Filename :
962696
Link To Document :
بازگشت