• DocumentCode
    1681455
  • Title

    Influence of load behavior on service restoration

  • Author

    Babnik, T. ; Gasperic, S. ; Gubina, A. ; Gubina, F.

  • Author_Institution
    Fac. of Electr. Eng., Ljubljana Univ., Slovenia
  • fYear
    1999
  • Firstpage
    116
  • Abstract
    An extended fault in a distribution system may pose problems during feeder restoration. Immediately after energizing the feeder, high currents may arise due to a phenomenon called cold load pick-up (CLPU), causing activation of the overcurrent protection and preventing immediate reconnection of all load. The feeder should be sectioned and the restoration performed in steps. In the paper, an algorithm for determination of a sequence of restoration actions is presented. The algorithm determines the maximum number of customers that can be reconnected immediately and recommends time delays to restore the remaining sections with regards to the setting of overcurrent protection. The results of a restoration simulation on a part of the Slovenian distribution system are presented in the paper.
  • Keywords
    load (electric); overcurrent protection; power distribution faults; power distribution protection; power system restoration; Slovenian distribution system; cold load pick-up; distribution system; extended fault; feeder energisation; feeder restoration; feeder sectioning; high currents; immediate load reconnection prevention; load behavior; overcurrent protection activation; service restoration; ste-by-step restoration; time delays; Automatic control; Delay effects; Load modeling; Protection; Steady-state; Student members; Testing; Voltage;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Electric Power Engineering, 1999. PowerTech Budapest 99. International Conference on
  • Conference_Location
    Budapest, Hungary
  • Print_ISBN
    0-7803-5836-8
  • Type

    conf

  • DOI
    10.1109/PTC.1999.826547
  • Filename