  • Title

    Lessons/experience learned from the Boston Edison Company control room enhancement project

  • Author

    Eisenmann, Norman R. ; Beith, Danna M. ; Shawver, Diane W.

  • Author_Institution
    Boston Edison Co., Boston, MA, USA
  • fYear
    1992
  • Firstpage
    287
  • Lastpage
    290
  • Abstract
    The Boston Edison Company implemented the first phase of a control room enhancement project at the Pilgrim Nuclear Power Station. The project consists of several tasks, such as control panel painting, control panel relabeling, an upgrade of the control room lighting, etc. These tasks implemented the corrective actions identified during one of the Three Mile Island (TMI)-related activities, i.e., the detailed control room design review (DCRDR). The control panel relabeling and painting tasks and the control room lighting upgrade are described. Issues that were identified in the implementation of these enhancements as well as lessons learned from these projects are discussed.<>
  • Keywords
    control facilities; nuclear power stations; power station computer control; Boston Edison Company; Pilgrim Nuclear Power Station; control panel painting; control panel relabeling; control room design review; control room enhancement project; control room lighting; Control systems; Design engineering; Hardware; Human factors; Labeling; Lighting control; Painting; Power generation; Switches; Systems engineering and theory;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Human Factors and Power Plants, 1992., Conference Record for 1992 IEEE Fifth Conference on
  • Conference_Location
    Monterey, CA, USA
  • Print_ISBN
    0-7803-0888-3
  • Type

    conf

  • DOI
    10.1109/HFPP.1992.283394
  • Filename