Integrating Risk Assessment and Actual Performance for Probabilistic Project Cost Forecasting: A Second Moment Bayesian Model
Author :
Byung-Cheol Kim
Author_Institution :
Dept. of Civil Eng., Ohio Univ., Athens, OH, USA
Volume :
62
Issue :
2
fYear :
2015
fDate :
42125
Firstpage :
158
Lastpage :
170
Abstract :
Forecasting the actual cost to complete a project is a critical challenge of project management, particularly for data-driven decision making in contingency control, cash flow analysis, and timely project financing. This paper presents a Bayesian project cost forecasting model that adaptively integrates preproject cost risk assessment and actual performance data into a range of possible project costs at a chosen confidence level. The second moment Bayesian (SMB) model brings more realism into project cost forecasting by explicitly accounting for inherent variability of cost performance, correlation between aggregated past and future performance, and the fraction of project completed at the time of forecasting. Functionally, the SMB model fully encompasses, as restrictive cases, two most commonly used index-based cost forecasting techniques in earned value management. The SMB model provides computationally efficient algebraic formulas to conduct robust probabilistic forecasting without additional burden of data collection or sophisticated statistical analysis. Numerical examples and simulation experiments are presented to demonstrate the predictive efficacy and practical applicability of the SMB in real project environments.
Keywords :
Bayes methods; costing; decision making; forecasting theory; project management; risk management; Bayesian project cost forecasting model; SMB model; cash flow analysis; contingency control; data-driven decision making; earned value management; index-based cost forecasting techniques; performance data; project cost risk assessment; project management; robust probabilistic forecasting; second moment Bayesian model; timely project financing; Bayes methods; Correlation; Forecasting; Gaussian distribution; Predictive models; Risk management; Standards; Bayesian; cost forecasting; cost risk; earned value management (EVM); project management;
fLanguage :
English
Journal_Title :
Engineering Management, IEEE Transactions on
Publisher :
ieee
ISSN :
0018-9391
Type :
jour
DOI :
10.1109/TEM.2015.2404935
Filename :
7058367
Link To Document :
بازگشت