  • Abstract
    Technical literature about live working has been mainly devoted to problems related to electrical insulation of the network, especially distances to maintain between linesmen and live parts. This paper concentrates on aspects related to current in electrical installations as it may become necessary, during live maintenance, to separate temporarily these installations from the network. Risk analysis results on limiting conditions expressed as maximum current values and/or length of installations which can be worked on are presented
  • Keywords
    maintenance engineering; personnel; power overhead lines; power transmission lines; safety; switching; electrical installations; live working; live-line maintenance; overhead power transmission lines; personnel safety; risk analysis; switching on by-pass currents; Dairy products; Dielectrics and electrical insulation; Moisture; Risk analysis; Voltage;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Transmission and Distribution Construction and Live Line Maintenance, 1993. Proceedings from ESMO-93., Sixth International Conference on
  • Conference_Location
    Las Vegas, NV
  • Print_ISBN
    0-7803-1340-2
  • Type

    conf

  • DOI
    10.1109/TDCLLM.1993.316241
  • Filename
    316241