DocumentCode :
2022781
Title :
Designing a transmission line using Pareto approach
Author :
Beryozkina, S. ; Sauhats, Antans ; Neimane, Viktoria
Author_Institution :
Fac. of Power & Electr. Eng., Riga Tech. Univ., Riga, Latvia
fYear :
2013
fDate :
16-20 June 2013
Firstpage :
1
Lastpage :
6
Abstract :
Transmission networks are facing an investment challenge due to the limited capacity of the existing power lines. Construction of the new overhead lines is associated with several legal, technical and economic problems. This paper describes Pareto approach for choosing the optimum design of the power line by minimizing the invested capital costs and maximizing the net present value. The analysis of presented solution including assessment of technical and economic efficiency is based on the model of a real line project. The results of the analysis are discussed in the paper.
Keywords :
Pareto optimisation; power overhead lines; power transmission planning; Pareto approach; economic efficiency; economic problems; invested capital costs; legal problems; net present value; overhead lines; power lines; real line project; technical efficiency; technical problems; transmission line; transmission networks; Conductors; Equations; Investment; Optimization; Poles and towers; Power transmission lines; Design engineering; Pareto optimization; electromagnetic fields; power transmission; transmission lines;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
PowerTech (POWERTECH), 2013 IEEE Grenoble
Conference_Location :
Grenoble
Type :
conf
DOI :
10.1109/PTC.2013.6652352
Filename :
6652352
Link To Document :
بازگشت