Flow shop scheduling problems with transportation and capacities constraints
Author
Oulamara, A. ; Soukhal, A.
Author_Institution
Lab. Recherche Operationnelle Leibniz, IMAG, Grenoble, France
Volume
4
fYear
2001
fDate
2001
Firstpage
2540
Abstract
In most manufacturing and distribution systems, semi-finished jobs are transferred from one processing facility to another and finished jobs are delivered to customers or warehouse by vehicles such as trucks. The paper investigates flow shop scheduling problems that explicitly consider constraints on both transportation and buffer capacities. These elements enable the flexible manufacturing systems (FMS) to process different types of parts. The finished jobs leave the processing facility to be delivered to customers or sent to warehouses by vehicles such as trucks. The objective function that is considered is makespan C max. We prove that this problem is strongly NP-hard when the capacity of truck is equal to two with unlimited buffer behind each machine. This problem with additional constraints, such as blocking, is also proved to be NP-hard
Keywords
computational complexity; flexible manufacturing systems; goods distribution; production control; transportation; NP-hard problem; blocking; capacities constraints; complexity; distribution systems; flexible manufacturing systems; flow shop scheduling problems; makespan; semi-finished jobs; transportation constraints; warehouses; Automatic control; Control systems; Flexible manufacturing systems; Job shop scheduling; Manufacturing automation; Manufacturing processes; Manufacturing systems; Production; Transportation; Vehicles;
fLanguage
English
Publisher
ieee
Conference_Titel
Systems, Man, and Cybernetics, 2001 IEEE International Conference on
Conference_Location
Tucson, AZ
ISSN
1062-922X
Print_ISBN
0-7803-7087-2
Type
conf
DOI
10.1109/ICSMC.2001.972940
Filename
972940
Link To Document