• DocumentCode
    2284725
  • Title

    Electrical system design, interface, and commissioning requirements for a large cogeneration project

  • Author

    Arvay, George J. ; Eisenrich, Brian L. ; Smith, Ray

  • Author_Institution
    Charles T. Main Inc., Pasadena, CA, USA
  • fYear
    1990
  • fDate
    7-12 Oct. 1990
  • Firstpage
    1793
  • Abstract
    The engineering methods, monitoring of design development, and onsite testing of a large, multiunit turnkey cogeneration project for thermally enhanced oil recovery are described. The system facility, electrical system requirements and criteria, major systems and equipment specifications, and system implementation are discussed. It is suggested that precise electrical design criteria must be developed and major equipment specifications must be detailed early in the design phase, and implementation must be monitored throughout the project to ensure coordination of interfaces between the gas turbine generator vendor, gas insulated substation equipment supplier, utility company, and the rest of the plant contractors.<>
  • Keywords
    cogeneration; commissioning; design engineering; gas turbine power stations; gaseous insulation; power systems; project engineering; substations; turbogenerators; GIS; cogeneration project; commissioning; design; development; gas insulated substation; gas turbine generator; interface; power stations; power systems; testing; thermally enhanced oil recovery; turbogenerators; turnkey; Cogeneration; Design engineering; Design methodology; Dielectrics and electrical insulation; Gas insulation; Monitoring; Petroleum; Testing; Thermal engineering; Turbines;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Industry Applications Society Annual Meeting, 1990., Conference Record of the 1990 IEEE
  • Conference_Location
    Seattle, WA, USA
  • Print_ISBN
    0-87942-553-9
  • Type

    conf

  • DOI
    10.1109/IAS.1990.152429
  • Filename
    152429