Title
Distribution System Monitoring and Control for the AEGEAN Islands: PPC´s Procurement of the New SCADA and DMS
Author
Silva, N. ; Champakis, M. ; Fountas, N. ; Voreadi, E.
Author_Institution
EFACEC, Maia, Portugal
fYear
2011
fDate
25-28 Sept. 2011
Firstpage
1
Lastpage
6
Abstract
Electrical distribution systems are evolving and becoming more flexible with the inclusion of more intelligent electronic devices (IED) and remote terminal units (RTU). This enables the optimization of the network operation giving the operator more information and control options. SCADA and DMS systems need to accommodate and efficiently process all the data and alarms and aid the operator in making the best possible choices in the lowest time. The criticality of the decision making process when operating an islanded system is even higher. This papers overviews the adequate technical architecture of a distribution management system for the Greek islands and details the essential functionalities required.
Keywords
SCADA systems; decision making; distributed power generation; power distribution control; power system management; power system measurement; AEGEAN island; DMS system; IED; PPC procurement; RTU; SCADA system; adequate technical architecture; decision making process; distribution management system; distribution system control; distribution system monitoring; intelligent electronic device; remote terminal unit; Laser modes; Local area networks; Modems; Optimization; Security; Switches; Training; Distributed control; Power system control; Power system management; Real time systems; SCADA systems; Substation automation;
fLanguage
English
Publisher
ieee
Conference_Titel
Intelligent System Application to Power Systems (ISAP), 2011 16th International Conference on
Conference_Location
Hersonissos
Print_ISBN
978-1-4577-0807-7
Electronic_ISBN
978-1-4577-0808-4
Type
conf
DOI
10.1109/ISAP.2011.6082216