• DocumentCode
    2383721
  • Title

    Slovenian Approach in Reliability Centered Maintenance of Transmission System Provider

  • Author

    Jamsek, Sasa ; Bakic, Kresimir

  • Author_Institution
    ELES
  • fYear
    2006
  • fDate
    21-24 May 2006
  • Firstpage
    799
  • Lastpage
    802
  • Abstract
    This paper deals with asset management and maintenance strategy in transmission utility, IT support and development of Slovenian national transmission network in the new deregulated environment of electric supply industry (ESI). After establishing new institutional arrangement of the Slovenian energy sector in accordance with a new Energy Act (1999), many solutions and previous paradigms have changed. New institutional arrangement started in 2001 with internal and in 2003 with external electricity market. Opening level of Slovenian electricity market is presently 75 %. Considering the new deregulated environment and new mechanism of asset management proceedings on one hand and constantly increasing consumption on the other hand, increasing loading of transmission network as well as a large level of parallel flows as consequence of location at crossroads of middle Europe with increasing power exchanges with Italy and other neighbors, Slovenian transmission provider was forced to introduce new approaches in asset management with aim to improve network efficiency and reliability. Optimization of asset management and particularly maintenance strategy as important element in the efficient network business was the most important task of company management, especially considering impacts of ageing to transmission system. ELES as the only Slovenian transmission provider selected package Maximo as general IT maintenance support and reliability centered maintenance (RCM) approach in maintenance strategy using package Calpos main. This paper addresses the connection between two supporting tools explaining first experiences in optimizing investment in new power transformer 300 MVA in transmission network. New RCM approach was implemented on the substations only and has shown that new approach can be very attractive from economical point of view. Estimated maintenance cost could be reduced up to 25 % with same reliability standard for customers
  • Keywords
    maintenance engineering; power markets; power transformers; power transmission reliability; 300 MVA; IT support; Maximo package; Slovenian electricity market; Slovenian national transmission network; asset management; deregulated environment; electric supply industry; network reliability; power exchanges; power transformer; reliability centered maintenance; transmission system provider; Asset management; Business; Companies; Electricity supply industry; Electricity supply industry deregulation; Europe; Maintenance; Packaging; Power system management; Power system reliability;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Transmission and Distribution Conference and Exhibition, 2005/2006 IEEE PES
  • Conference_Location
    Dallas, TX
  • Print_ISBN
    0-7803-9194-2
  • Type

    conf

  • DOI
    10.1109/TDC.2006.1668598
  • Filename
    1668598