  • Abstract
    New technologies and methods have been applied to a 230 kV transmission line uprating project. Significant savings have been documented in field investigation efforts, data collection, design time, line outages and construction costs. Advancements in software and data collection instruments have been combined with innovative line engineering to improve the accuracy and reduce the costs of uprating projects. Laser surveying, span-by-span resagging and conductor temperature measurements have been combined to increase the ampacity rating by 30%, at a fraction of the cost of traditional uprating.
  • Keywords
    maintenance engineering; power transmission lines; project engineering; 230 kV; ampacity rating; conductor temperature measurements; construction costs; data collection; design time; field investigation; laser surveying; line outages; span-by-span resagging; transmission line uprating technologies; uprating project; Circuits; Clamps; Conductors; Costs; Insulation; Performance evaluation; Power transmission lines; Temperature; Transmission lines; Wire;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Transmission & Distribution Construction, Operation & Live-Line Maintenance Proceedings, 1998. ESMO '98. 1998 IEEE 8th International Conference on
  • Conference_Location
    Orlando, FL, USA
  • Print_ISBN
    0-7803-4883-4
  • Type

    conf

  • DOI
    10.1109/TDCLLM.1998.668396
  • Filename
    668396