Time-constraint activities scheduling
Author :
Nazirkar, Reshma R. ; Sambhaji, Gawade Jawahar
Author_Institution :
Comput. Dept., SVPM´s COE, Pune, India
fYear :
2014
fDate :
9-11 May 2014
Firstpage :
1
Lastpage :
5
Abstract :
Many software project lag behind schedule because in actual work activity duration get changed due to unexpected things, hence this study considers different duration types of the same activity. This system considers activity which is time-dependent, random and normal. Objective is to schedule software project using time-dependent and random activities within deadline. This type of project cannot be schedule using simple critical path method. Hence we integrate critical path method and stochastic technique to find stochastic critical path.
Keywords :
critical path analysis; genetic algorithms; project management; scheduling; software management; stochastic processes; critical path method; genetic processes; random activities; software project scheduling; stochastic critical path model; stochastic technique; time-constraint activity scheduling; time-dependent activities; uncertainty genetic algorithm; Biological cells; Probabilistic logic; Probes; Reactive power; Software; Genetic optimization; Stochastic Critical path;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Recent Advances and Innovations in Engineering (ICRAIE), 2014
Conference_Location :
Jaipur
Print_ISBN :
978-1-4799-4041-7
Type :
conf
DOI :
10.1109/ICRAIE.2014.6909196
Filename :
6909196
Link To Document :
بازگشت