DocumentCode :
2547444
Title :
The impact of time-cost tradeoff on the Internal Rate of Return for hydropower construction
Author :
Xun, Liu ; Zhuo-Fu, Wang
Author_Institution :
Inst. of Constr. Project Manage., Hohai Univ., Nanjing, China
fYear :
2010
fDate :
16-18 April 2010
Firstpage :
208
Lastpage :
213
Abstract :
The previous approach solved the time-cost tradeoff problem without considering the impact of Internal Rate of Return (IRR) of the project. The present paper incorporates it into project time-cost tradeoff for hydropower construction. The research on performance and the tradeoffs between time-cost and performance is of significance when the lasting time of the construction is uncertain. It is also pointed out that the relative importance of each activity for managerial purposes in polynomial time because the probability that each activity will be critical. The methodology provides the means to obtain the optimal time-cost scheduling of expected completion times as well as the variability in these time, cost and performance estimates. Two examples of hydropower construction are used to demonstrate the application.
Keywords :
hydroelectric power stations; power generation scheduling; hydropower construction; internal rate of return; polynomial time; probability; time-cost tradeoff; Computer crashes; Computer network management; Cost function; Hydroelectric power generation; Linear programming; Piecewise linear approximation; Piecewise linear techniques; Polynomials; Processor scheduling; Project management; internal rate of return; project management; schedule network; time-cost tradeoff;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Information Management and Engineering (ICIME), 2010 The 2nd IEEE International Conference on
Conference_Location :
Chengdu
Print_ISBN :
978-1-4244-5263-7
Electronic_ISBN :
978-1-4244-5265-1
Type :
conf
DOI :
10.1109/ICIME.2010.5477783
Filename :
5477783
Link To Document :
بازگشت