    This paper describes the execution of a conductor cable replacement of damaged parts in a 138 kV double circuit transmission line. The conductor cable of the mentioned line, presented accentuated creep signs as well as damage and considering the utility of increasing the transmission line rating the utility decided to replace the conductor cable in the sags where these problems were more evident. There were many operational difficulties that determined that the job had to be done using live line technique, and for this purpose Hot Line Construcoes Eletricas was hired, and executed the job
  • Keywords
    maintenance engineering; overhead line conductors; power overhead lines; 138 kV; Hot Line Construcoes Eletricas; accentuated creep; conductor cable replacement; double circuit transmission line; energized transmission line; live line technique; sags; transmission line rating increase; Concrete; Conductors; Contacts; Creep; Distributed parameter circuits; Explosions; Poles and towers; Power cables; Safety; Transmission lines;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Transmission and Distribution Construction, Operation and Live-Line Maintenance Proceedings. 2000 IEEE ESMO - 2000 IEEE 9th International Conference on
  • Conference_Location
    Montreal, Que.
  • Print_ISBN
    0-7803-6625-5
  • Type

    conf

  • DOI
    10.1109/TDCLLM.2000.882859
  • Filename
    882859