  • Title

    Commissioning of the 1 MW spallation neutron source SINQ

  • Author

    Bauer, G.S. ; Fischer, W.E. ; Rohrer, U. ; schryber, U.

  • Author_Institution
    Paul Scherrer Inst., Villigen, Switzerland
  • Volume
    3
  • fYear
    1997
  • fDate
    12-16 May 1997
  • Firstpage
    3785
  • Abstract
    First beam tests were carried out successfully on the spallation neutron source SINQ at Switzerland´s Paul Scherrer Institut (PSI) in December 1996. SINQ is driven by the PSI 590 MeV isochronous cyclotron which is now operating routinely at a current level around 1.5 mA. After running at 20 μA for several hours to enable radiation surveys and neutron beam measurements on December 3, the current was raised in steps to its maximum value within 3.5 hours on December 4, making the power on SINQ the highest one ever reached on a spallation target so far. The tests allowed measurements of neutron and gamma radiation levels around and in the extracted neutron beams and guides and included beam transport studies in the new section of the proton beam line. At the same time the whole target system including its cold neutron moderator was tested successfully
  • Keywords
    commissioning; cyclotrons; neutron sources; proton accelerators; 1 MW; 590 MeV; SINQ; beam transport; cold neutron moderator; isochronous cyclotron; neutron beams; spallation neutron source; Acceleration; Current measurement; Cyclotrons; Magnets; Neutrons; Particle beams; Power measurement; Proton accelerators; Testing; Voltage;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Particle Accelerator Conference, 1997. Proceedings of the 1997
  • Conference_Location
    Vancouver, BC
  • Print_ISBN
    0-7803-4376-X
  • Type

    conf

  • DOI
    10.1109/PAC.1997.753416
  • Filename
    753416