Risk Management Method Using Data from EVM in Software Development Projects
Author
Hayashi, Akihiro ; Kataoka, Nobuhiro
Author_Institution
Resource & Capacity Manage., IBM Japan, Tokyo, Japan
fYear
2008
fDate
10-12 Dec. 2008
Firstpage
1135
Lastpage
1140
Abstract
The main objective of risk management is to reduce factors that will give negative influence to project. However, it is difficult to specify the risk of actualizing beforehand. In this paper, we first analyze real cases of software development projects that adopted risk management but failed, and identify the root causes. Next, we propose a permanent monitoring agency that predicts future risks generation using quantitative data captured by earned value management technique. The proposal of this paper was applied an actual software development organization and ensured effectiveness.
Keywords
risk management; software development management; earned value management technique; permanent monitoring agency; quantitative data; risk management method; risks generation; software development projects; Cause effect analysis; Delay estimation; Failure analysis; Programming; Project management; Proposals; Resource management; Risk analysis; Risk management; Software development management; Earned Value Analysis; Risk Management; Software Process;
fLanguage
English
Publisher
ieee
Conference_Titel
Computational Intelligence for Modelling Control & Automation, 2008 International Conference on
Conference_Location
Vienna
Print_ISBN
978-0-7695-3514-2
Type
conf
DOI
10.1109/CIMCA.2008.72
Filename
5172785
Link To Document