• DocumentCode
    276270
  • Title

    The integration of new valves and controls to Nelson River HVDC Bipole 1

  • Author

    Goodrich, F.G. ; Haddock, J.L. ; Rowe, B.A. ; Thanawala, H.L. ; Willis, D.B.

  • Author_Institution
    GEC ALSTHOM Tansmission & Distribution Projects Ltd., Stafford, UK
  • fYear
    1991
  • fDate
    17-20 Sep 1991
  • Firstpage
    147
  • Lastpage
    152
  • Abstract
    The Nelson River HVDC transmission system in Manitoba presently consists of two bipoles. Bipole 1 has a rating of 1670 MW at ±463 kV and transmits this power from the northern terminal at Radisson Station over a distance of approximately 900 km to the Dorsey terminal near Winnipeg. Bipole 2 has a rating of 1800/2000 MW at ±500 kV and transmits this power from the Henday Station, some 40 km downstream from Radisson, also to the Dorsey terminal. Bipole 1 which is the subject of this article, was the last of the HVDC links to be commissioned using mercury arc power convertor valves. The rating of 154.5 kV, 1800 Å per group is the highest used for mercury arc convertor valves
  • Keywords
    DC power transmission; maintenance engineering; mercury arc rectifiers; project engineering; switchgear; transmission networks; 154.5 kV; 1670 MW; 1800 AA; 463 kV; Canada; HVDC; bipoles; links; mercury arc power convertor valves; project; rating; switchgear; transmission system;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    AC and DC Power Transmission, 1991., International Conference on
  • Conference_Location
    London
  • Print_ISBN
    0-85296-517-6
  • Type

    conf

  • Filename
    153895