    Optimization of Bonus-Penalty Structure in Flexible Resources-Constrained Project Scheduling Problems from Both Sides of the Contract

  • Author

    Chai, Guorong ; Huang, Shitao ; Zhang, Guoxing ; Su, Yana

  • Author_Institution
    Sch. of Manage., Lanzhou Univ., Xi´´an, China
  • fYear
    2010
  • fDate
    13-15 Aug. 2010
  • Firstpage
    109
  • Lastpage
    113
  • Abstract
    Project contractors often need to rent resources to execute their projects, and the clients often set up bonus-penalty structure (BP-structure) at the deadline of the project to encourage the contractors in fulfilling the project on time. In this paper, we introduce BP-structure and flexible resource-constraints (i.e. resource renting) into traditional RCPSP, and formulate an optimization model of BP-structure based on flexible resource-constraints from both sides of the contract. By solving the model the contractor gets optimal schedule and the client obtains optimal bonus-penalty rate (BP-rate) to a given due date. Both sides of the contract can obtain maximal incomes under the optimal schedule with the optimal BP-rate. Finally, the outcomes of the paper are illustrated by a numerical example.
  • Keywords
    contracts; incentive schemes; optimisation; project management; scheduling; bonus-penalty structure; flexible resources-constrained project scheduling; optimization; project contractors; Contracts; Europe; Indexes; Mathematical model; Optimal scheduling; Schedules; bonus-penalty rate (BP-rate); bonus-penalty structure (BP-structure); flexible resource-constraints; project scheduling problem (PSP);
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Business Intelligence and Financial Engineering (BIFE), 2010 Third International Conference on
  • Conference_Location
    Hong Kong
  • Print_ISBN
    978-1-4244-7575-9
  • Type

    conf

  • DOI
    10.1109/BIFE.2010.35
  • Filename
    5621740