Transport and installation of the LHC cryo-magnets
Author :
Artoos, K. ; Bartolome-Jimenez, S. ; Capatina, O. ; Chevalley, J.M. ; Foraz, K. ; Guinchard, M. ; Hauviller, C. ; Kershaw, K. ; Prodon, S. ; Ruehl, I. ; Trinquart, G. ; Weisz, S. ; Ponsot, P.
Author_Institution :
CERN, Geneva
fYear :
2007
fDate :
25-29 June 2007
Firstpage :
305
Lastpage :
307
Abstract :
Eleven years have passed between the beginning of transport and handling studies in 1996 and the completion of the LHC cryo-magnets installation in 2007. More than 1700 heavy, long and fragile cryo-magnets had to be transported and installed in the 27 km long LHC tunnel with very restricted available space. The size and complexity of the project involved challenges in the field of equipment design and manufacturing, maintenance, training and follow-up of operators and logistics. The paper presents the milestones, problems to be overcome and lessons learned during this project.
Keywords :
accelerator magnets; ion accelerators; proton accelerators; storage rings; synchrotrons; LHC cryomagnets installation; cryomagnet transport; equipment design; handling technique; magnet logistics; welding machines; Cranes; Large Hadron Collider; Lifting equipment; Logistics; Magnets; Manufacturing; Satellite broadcasting; Space technology; Testing; Vehicles;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Particle Accelerator Conference, 2007. PAC. IEEE
Conference_Location :
Albuquerque, NM
Print_ISBN :
978-1-4244-0916-7
Type :
conf
DOI :
10.1109/PAC.2007.4440193
Filename :
4440193
Link To Document :
بازگشت