DocumentCode
2915787
Title
Design Analysis of the Selection of the Four Main Pipelines of the 1000MW Ultra Supercritical Unit
Author
Ying-Bai, Xie ; Shao-Heng, Wang ; Bing, Li ; Yun, Liu
Author_Institution
North China Electr. Power Univ., Baoding, China
fYear
2011
fDate
19-20 Feb. 2011
Firstpage
155
Lastpage
157
Abstract
Pipelines for the main steam, hot sections of the reheat steam, cold sections of the reheat steam and the high pressure feed water are main constitutes of the power plant boiler. Material selection of the four main pipelines will have significant impact on the security and economy of the power plant operation. The pressure of the main steam of the 1000MW ultra supercritical unit in Tianjin SDIC Jinneng Electric Power CO.LTD is 27.56 MPa, and the temperature of the main steam is 605°C. It brings forward the high requirement of the mechanical characteristic and high temperature performance of the four main pipelines. Demonstration is processed considering the thermal stress, coefficient of the heat expansion, operation reliability and the economy, and the compositions of the four main pipeline material are selected.
Keywords
boilers; maintenance engineering; pipelines; power generation reliability; steam power stations; thermal stresses; heat expansion coefficient; high pressure feed water; pipeline material; power 1000 MW; power plant boiler; power plant economy; pressure 27.56 MPa; steam reheating; temperature 605 degC; thermal stress; ultrasupercritical unit; Computers; Distributed control; Monitoring; Design; Main pipeline; Material; Supercritical unit;
fLanguage
English
Publisher
ieee
Conference_Titel
Computer Distributed Control and Intelligent Environmental Monitoring (CDCIEM), 2011 International Conference on
Conference_Location
Changsha
Print_ISBN
978-1-61284-278-3
Electronic_ISBN
978-0-7695-4350-5
Type
conf
DOI
10.1109/CDCIEM.2011.416
Filename
5747786
Link To Document