Abstract :
This paper describes a hydroelectric power station control systempsilas update process project. The project pursued the following objectives: to improve operation of the hydroelectric power station by implementing modern technology; to provide redundancy for critical functions; to extract the maximum amount of process information and make it available to the organization in a timely fashion to make business decisions in real time, with less errors; to establish the behavior of the equipment in order to be able to reduce power consumption of the generation power station; and finally, to implement the complete project over a short period of time, with minimal costs.
Keywords :
decision making; hydroelectric power stations; power consumption; power station control; real-time systems; redundancy; critical function redundancy; hydro-electric plant control system; power consumption reduction; power station operation; real time business decision making; Automatic control; Availability; Business; Control systems; Databases; Information retrieval; Power generation; Process control; Redundancy; Substations; Internet; Programming; Redundancy; Relational databases; SCADA systems; Security;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Transmission and Distribution Conference and Exposition: Latin America, 2008 IEEE/PES
Conference_Location :
Bogota
Print_ISBN :
978-1-4244-2217-3
Electronic_ISBN :
978-1-4244-2218-0
Type :
conf
DOI :
10.1109/TDC-LA.2008.4641758
Filename :
4641758
Link To Document :
بازگشت