DocumentCode
3105597
Title
Maximum loadability achievement in SWER networks using optimal sizing and locating of batteries
Author
Arefi, Ali ; Ledwich, Gerard
Author_Institution
Sch. of Electr. Eng. & Comput. Sci., Queensland Univ. of Technol., Brisbane, QLD, Australia
fYear
2013
fDate
Sept. 29 2013-Oct. 3 2013
Firstpage
1
Lastpage
6
Abstract
This paper presents an optimisation algorithm to maximize the loadability of single wire earth return (SWER) by minimizing the cost of batteries and regulators considering the voltage constraints and thermal limits. This algorithm, that finds the optimum location of batteries and regulators, uses hybrid discrete particle swarm optimization and mutation (DPSO + Mutation). The simulation results on realistic highly loaded SWER network show the effectiveness of using battery to improve the loadability of SWER network in a cost-effective way. In this case, while only 61% of peak load can be supplied without violating the constraints by existing network, the loadability of the network is increased to peak load by utilizing two battery sites which are located optimally. That is, in a SWER system like the studied one, each installed kVA of batteries, optimally located, supports a loadability increase as 2 kVA.
Keywords
battery storage plants; distributed power generation; earthing; particle swarm optimisation; voltage regulators; DPSO + Mutation; SWER networks; apparent power 2 kVA; discrete particle swarm optimization and mutation; maximum loadability; optimal sizing and locating; optimisation algorithm; single wire earth return; Australia; Batteries; Educational institutions; Optimization; Regulators; Standards; Voltage control; DPSO; Loadability; SWER; battery; mutation; optimal sizing and locating; regulator;
fLanguage
English
Publisher
ieee
Conference_Titel
Power Engineering Conference (AUPEC), 2013 Australasian Universities
Conference_Location
Hobart, TAS
Type
conf
DOI
10.1109/AUPEC.2013.6725472
Filename
6725472
Link To Document