DocumentCode
3141678
Title
Temporary Ground Fault Path Clearing system for power distribution system
Author
Sutanto, Jusmin ; Pujihatma, Priambudi ; Widjaja, Radpandji Edy
Author_Institution
Dept. of Power Generation & Transm., PT Chevron Pacific Indonesia, Indonesia
fYear
2012
fDate
3-5 July 2012
Firstpage
1
Lastpage
5
Abstract
This paper presents an alternative method to improve the reliability of power distribution system against temporary ground fault by means of a recloser inserted between neutral point of substation power transformer and the grounding resistor. This recloser trips when there is ground fault at the feeder and reclose on a preset time delay. If the fault is sustaining, the grounding recloser will close permanently and the traditional overcurrent protection takes place. The field trial confirmed the effectiveness of the proposed method. The method is named as Ground Fault Path Clearing system or GFPC for short.
Keywords
delays; earthing; overcurrent protection; power distribution faults; power distribution reliability; power transformers; substation protection; GFPC; feeder; grounding recloser; grounding resistor; neutral point; overcurrent protection; power distribution system reliability; recloser trips; substation power transformer; temporary ground fault path clearing system; time delay; Grounding; Interrupters; Power transformers; Production; Relays; Reliability; Substations; GFPC; grounding recloser; temporary ground fault;
fLanguage
English
Publisher
ieee
Conference_Titel
Power Engineering and Renewable Energy (ICPERE), 2012 International Conference on
Conference_Location
Bali
Print_ISBN
978-1-4673-2468-7
Electronic_ISBN
978-1-4673-2469-4
Type
conf
DOI
10.1109/ICPERE.2012.6287220
Filename
6287220