Title :
Installation and Radiation Maintenance Scenario for J-PARC 50 GeV Synchrotron
Author :
Yoshioka, M. ; Kobayashi, H. ; Oogoe, T. ; Takeuchi, Y. ; Watanabe, Y. ; Kuniyasu, Y. ; Oki, H. ; Takiyama, Y.
Author_Institution :
KEK, Tsukuba, Japan, masakazu.yoshioka@kek.jp
fYear :
2005
fDate :
16-20 May 2005
Firstpage :
835
Lastpage :
837
Abstract :
The accelerator tunnel of the J-PARC 50 GeV Synchrotron is still under construction, and will be completed at the end of 2006. Installation of accelerator-components is scheduled to start in July 2005 in parallel with civil and utility construction, and beam commissioning will be started in January 2008. This document describes how to install accelerator components in the tunnel and a radiation maintenance scenario.
Keywords :
Acceleration; Collimators; Concrete; Floors; Linear accelerators; Linear particle accelerator; Particle beams; Sea surface; Structural beams; Synchrotron radiation;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Particle Accelerator Conference, 2005. PAC 2005. Proceedings of the
Print_ISBN :
0-7803-8859-3
Type :
conf
DOI :
10.1109/PAC.2005.1590580
Filename :
1590580
Link To Document :
بازگشت