    Status of the IUCF cooler injector synchrotron

  • Author

    Friesel, D.L. ; Lee, S.Y.

  • Author_Institution
    Cyclotron Facility, Indiana Univ., Bloomington, IN, USA
  • Volume
    1
  • fYear
    1997
  • fDate
    12-16 May 1997
  • Firstpage
    935
  • Abstract
    Construction of a 2.24 T-m, rapid-cycling booster synchrotron is nearing completion at IUCF designed to accelerate protons to 220 MeV, it will replace the k200 isochronous cyclotron as an injector of polarized light ion beams (p,d) into the Indiana Cooler. The CIS (cooler injector synchrotron) will fill the Cooler to about 1011 protons in a few seconds for research. At 30 months into the construction program, all major ring elements are fabricated, assembled, installed and in some cases, commissioned. Ring strip injection and accumulation studies began in March, 1997, ramping studies will start in June, 1997 and Cooler injection studies are planned for late 1997. The status of the construction project and initial beam injection and commissioning results are presented
  • Keywords
    particle beam injection; proton accelerators; storage rings; synchrotrons; 220 MeV; IUCF; accumulation; commissioning; cooler injector synchrotron; injection; ramping; rapid-cycling booster synchrotron; Acceleration; Assembly; Computational Intelligence Society; Cyclotrons; Ion beams; Optical polarization; Protons; Strips; Structural beams; Synchrotrons;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Particle Accelerator Conference, 1997. Proceedings of the 1997
  • Conference_Location
    Vancouver, BC
  • Print_ISBN
    0-7803-4376-X
  • Type

    conf

  • DOI
    10.1109/PAC.1997.749886
  • Filename
    749886