Deploying a large-scale PMU system for the Brazilian interconnected power system
Author :
Moraes, Rui M. ; Volskis, Hector A R ; Hu, Yi
Author_Institution :
ONS, Rio de Janeiro
fYear :
2008
fDate :
6-9 April 2008
Firstpage :
143
Lastpage :
149
Abstract :
Recent power system blackouts around the world have driven attention to the need of wide area measurement, protection and control (WAMPAC) systems. Currently, the Brazilian electric power industry is making an effort, lead by independent system operator ONS, to implement a large-scale wide-area measurement system utilizing the synchronized phasor measurement technology. The system will be utilized to realize many off-line and real-time operation applications for improving the reliability and economical operations of the national interconnected power system (NIPS). The novelty of the technology and the task to implement such a system in a deregulated environment present some special challenges to the project and ONS. This paper describes the overall approach that the Brazilian power industry and ONS had adopted in implementing this system. The approach aims to address several main aspects of the project that are critical for a successful implementation of the system, such as the regulatory framework, under which the system is to be deployed, deployment planning, and overall system performance assurance measures. The project has successfully completed the system architecture design and corresponding system components specifications. ONS is currently in the process to hire a qualified test entity to perform the PMU homologation testing and calibration.
Keywords :
phase measurement; power system control; power system economics; power system faults; power system interconnection; power system measurement; power system protection; power system reliability; Brazilian interconnected power system; large-scale PMU system; national interconnected power system; power system blackouts; real-time operation applications; synchronized phasor measurement technology; wide area measurement protection and control; Large-scale systems; Phasor measurement units; Power system control; Power system interconnection; Power system measurements; Power system protection; Power system reliability; Power systems; Testing; Wide area measurements; PMU performance test and calibration; Synchrophasor; Wide-area measurement;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Electric Utility Deregulation and Restructuring and Power Technologies, 2008. DRPT 2008. Third International Conference on
Conference_Location :
Nanjuing
Print_ISBN :
978-7-900714-13-8
Electronic_ISBN :
978-7-900714-13-8
Type :
conf
DOI :
10.1109/DRPT.2008.4523392
Filename :
4523392
Link To Document :
بازگشت