DocumentCode
3468006
Title
Accelerate protection scheme in integrated protection system
Author
Zhang, Hao ; He, Jinghan ; Yip, Tony ; Bo, Z.Q.
Author_Institution
Beijing Jiaotong Univ., Beijing, China
fYear
2011
fDate
5-7 Dec. 2011
Firstpage
1
Lastpage
4
Abstract
Transformer is one of the most important elements in power system, and current differential protection has been the main protection technique for transformer unit. This protection technique, however, suffers a low sensitivity or reliability due to the problems such as CT saturation and transformer magnetizing inrush. Based on digital substation system, studies have found that the fault generated electric quantities can not only be used by the relay to achieve the line protection but also used for developing transformer protection techniques. The protection system can accelerate trip time if fault happen. The results from simulation test show that the new method is with simple principle and good reliability.
Keywords
power generation faults; power generation reliability; substation protection; transformer protection; CT saturation; accelerate protection scheme; current differential protection; digital substation system; fault generated electric quantities; integrated protection system; reliability; transformer magnetizing inrush; transformer protection; Automation; Circuit faults; Communication networks; Educational institutions; Power transformers; Relays; Substations; Digital systems; Power transformer protection; Substation communication system;
fLanguage
English
Publisher
ieee
Conference_Titel
Innovative Smart Grid Technologies (ISGT Europe), 2011 2nd IEEE PES International Conference and Exhibition on
Conference_Location
Manchester
ISSN
2165-4816
Print_ISBN
978-1-4577-1422-1
Electronic_ISBN
2165-4816
Type
conf
DOI
10.1109/ISGTEurope.2011.6162719
Filename
6162719
Link To Document