  • Abstract
    To meet the challenges of operating in a competitive electricity market NGC (National Grid Company) has adopted an engineering life cycle analysis, which focuses on the four stages of plant and system life, namely, design, buy and build, operate, and monitor and maintain. NGC´s R&D programme uses the same principles in focussing on day-to-day engineering issues so as to improve system reliability and flexibility, through the incorporation of new plant and technology, as well as, increasing the capability and availability of existing plant, and planning for the future. Some examples are given, from all four stages of the plant/system life cycle curve, in which NGC is actively pursuing research to meet the challenges it faces operating in an ever changing and competitive electricity market
  • Keywords
    electricity supply industry; National Grid Company; R&D programme; buy and build; competitive electricity market; day-to-day engineering issues; engineering life cycle analysis; innovative design; maintenance planning; monitor and maintain; operate; plant/system life cycle curve; software tools; system design; system flexibility improvement; system reliability improvement; transmission system operation;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    High Voltage Engineering, 1999. Eleventh International Symposium on (Conf. Publ. No. 467)
  • Conference_Location
    London
  • ISSN
    0537-9989
  • Print_ISBN
    0-85296-719-5
  • Type

    conf

  • DOI
    10.1049/cp:19990960
  • Filename
    818312