    The National Power Corporation (TNB) have ordered and placed into operation three static VAr compensation systems (SVCs) at its Kuala Lumpur North (KLN) and Yong Peng (YP) substations. The project was commissioned in the middle of 1991, and over the last one and a half years, TNB have gained considerable experience in operation and maintenance of the plant. The SVCs were ordered after an extensive planning study and system simulation. Each SVC plant is designed to operate in tandem with four breaker switched reactors rated at 25 MVAr each. Here, the author documents the experience gained during the operation of these plants.<>
  • Keywords
    compensation; power capacitors; power systems; project engineering; reactive power; static VAr compensators; substations; 25 MVA; 275 kV; Malaysia; breaker switched reactors; experience; maintenance; operation; power capacitors; power systems; project; static VAr compensation; substations; Cities and towns; Damping; Investments; Power generation; Power system planning; Reactive power; Static VAr compensators; Steady-state; Substations; Voltage control;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power Conversion Conference, 1993. Yokohama 1993., Conference Record of the
  • Conference_Location
    Yokohama, Japan
  • Print_ISBN
    0-7803-0471-3
  • Type

    conf

  • DOI
    10.1109/PCCON.1993.264188
  • Filename
    264188