• DocumentCode
    3775639
  • Title

    W7-X commissioning: Progress and lessons learned for future devices

  • Author

    F. Schauer;H.-S. Bosch;H. P. Laqua;T. S. Pedersen

  • Author_Institution
    Max-Planck-Institute for Plasma Physics, D-17491 Greifswald, Germany
  • fYear
    2015
  • fDate
    5/1/2015 12:00:00 AM
  • Firstpage
    1
  • Lastpage
    8
  • Abstract
    Commissioning of the stellarator Wendelstein 7-X (W7-X) at the Max-Planck-Institute for Plasma Physics in Greifswald, Germany, started in April 2014, simultaneously with final assembly work. First, individual components and their local control systems were put into operation. The subsequent cryostat evacuation was then the first large system commissioning. Before the final room temperature vacuum of ≈10-4 mbar was reached, the electrical insulation of the superconducting coil system had been successfully tested with voltages up to 2.5 kV under Paschen conditions. Partly in parallel, all power supplies, the trim and most of the control coils, CoDaC, and the diagnostic as well as ECRH - as far as possible without plasma - were put into operation. Next major achievements were the magnet system cool-down to 3.8 K, and the first operation of individual coil groups. Evacuation of the plasma vessel has been delayed due to leaks at vacuum pump manifold flanges which are currently being repaired. The large system commissioning steps and problems encountered as well as remedies are described, and an outlook for remaining work to be done until the first plasma is given.
  • Keywords
    "Coils","Plasmas","Helium","Insulation","Cooling","Superconducting magnets","Conductors"
  • Publisher
    ieee
  • Conference_Titel
    Fusion Engineering (SOFE), 2015 IEEE 26th Symposium on
  • Electronic_ISBN
    2155-9953
  • Type

    conf

  • DOI
    10.1109/SOFE.2015.7482423
  • Filename
    7482423