The Influence on an Activity´s Total Float of a Change in its Duration in Networks with Generalized Precedence Relations (GPRs)
Author
Cui, Wanan ; Qin, Jiajun ; Yue, Chaoyuan
Author_Institution
Huazhong Univ. of Sci. & Technol., Wuhan
Volume
1
fYear
2006
fDate
8-11 Oct. 2006
Firstpage
699
Lastpage
702
Abstract
This paper proposes the concepts of node´s early (later) realization time (ER, LR), node´s early (later) possible realization time (EPR, LPR), and gives the formulas of ER, LR, EPR, LPR, total float. And then, we classify the preconditions which determine the change of activities´ total floats. Furthermore, the laws of the influence of a change in an activity´s duration on its total float are explored and a computational example is presented.
Keywords
commerce; activity duration; activity total float; generalized precedence relations; realization time; Chaos; Control systems; Cybernetics; Delay estimation; Erbium; Ground penetrating radar; Helium; Paramagnetic resonance; Project management; Risk management;
fLanguage
English
Publisher
ieee
Conference_Titel
Systems, Man and Cybernetics, 2006. SMC '06. IEEE International Conference on
Conference_Location
Taipei
Print_ISBN
1-4244-0099-6
Electronic_ISBN
1-4244-0100-3
Type
conf
DOI
10.1109/ICSMC.2006.384467
Filename
4273914
Link To Document