Sizing and selection of grounding transformers-decision criteria
Author
Eduful, George ; Mensah, Godfred
Author_Institution
Syst. Planning Div., Electr. Co. of Ghana, Accra-North, Ghana
fYear
2011
fDate
7-10 Nov. 2011
Firstpage
45
Lastpage
49
Abstract
Within a period of two years, the Electricity Company of Ghana (ECG) lost a total of six grounding transformers in a particular substation. The situation created a lot of instability and resulted in huge productivity losses to both the company and its customers. The failures were believed to be related to wrong selection of grounding transformer rating. However, using the concept of capacitive charging current of a system, it was found that the short time rating of the grounding transformers were rightly selected. Analysis of the phenomenon strongly linked the damages to protection deficiency. This paper discusses analysis of the problem and proposes decision criteria for selecting a grounding transformer.
Keywords
decision making; earthing; power system protection; power transformers; substations; Electricity Company of Ghana; capacitive charging current; decision criteria; grounding transformer rating; grounding transformer selection; grounding transformer sizing; productivity loss; protection deficiency; Cable insulation; Grounding; Resistance; Transient analysis; Voltage control; Capacitive charging current; Grounding transformer; Zero sequence impedance; short time rating current;
fLanguage
English
Publisher
ieee
Conference_Titel
Sustainable Technologies (WCST), 2011 World Congress on
Conference_Location
London
Print_ISBN
978-1-4577-1311-8
Type
conf
Filename
6114236
Link To Document