DocumentCode :
572362
Title :
A Black-Start Field Test in Shandong Power Grid of China
Author :
Wang, Chunyi ; Li, Xueliang ; Lv, Tianguang ; Lei, Ming ; Fu, Lei ; Niu, Xinsheng
Author_Institution :
Shandong Electr. Power Res. Inst., Jinan, China
fYear :
2012
fDate :
27-29 March 2012
Firstpage :
1
Lastpage :
4
Abstract :
This paper discusses a black-start field test performed with new strategy. The new strategy makes full use of the long time operation capability of pumped storage units in ultra-low load conditions and takes advantage of the double-bar configuration of most electrical stations, with black-start units only supplying the auxiliary load of itself and that of target units, enables a complete separation of restoration path from distribution and the other transmission networks, avoiding any disturbance to customers during restoration field test. This feature improves the reliability of restoration plans, makes field test process repeatable and predictable. Field test of Shandong power grid in China verified the feasibility of this new strategy and the possibility of applying it in other areas which use pumped storage units as cranking power.
Keywords :
power generation planning; power grids; pumped-storage power stations; China; Shandong power grid; auxiliary load; black-start field test; distribution network; double-bar configuration; electrical stations; operation capability; pumped storage units; restoration path separation; restoration plan reliability; transmission network; ultralow-load conditions; Generators; Power generation; Power grids; Power system stability; Synchronization; Transient analysis;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Power and Energy Engineering Conference (APPEEC), 2012 Asia-Pacific
Conference_Location :
Shanghai
ISSN :
2157-4839
Print_ISBN :
978-1-4577-0545-8
Type :
conf
DOI :
10.1109/APPEEC.2012.6307694
Filename :
6307694
Link To Document :
بازگشت