• DocumentCode
    602420
  • Title

    Grid connection costs for renewable energy plants in Greece

  • Author

    Bada, Aikaterini I. ; Perrakis, Konstantinos G.

  • Author_Institution
    Heron Thermoelectric S.A., Athens, Greece
  • fYear
    2012
  • fDate
    1-3 Oct. 2012
  • Firstpage
    1
  • Lastpage
    6
  • Abstract
    In this paper an analysis of the costs of Grid Connection of renewable energy plants in Greece is performed. The analysis is limited to wind power and photovoltaic plants, as they represent the large majority of RES plants currently installed in Greece in order to meet the national targets of 20-2020 by year 2020. The analysis is based on ex-ante information available in connection offers provided to RES generators by the competent grid operators; it includes the following categories: (a) wind energy plants to be connected to the transmission system and to be installed on the mainland, on interconnected islands and on non-interconnected islands and (b) photovoltaic plants to be installed on the mainland and to be connected to the transmission or distribution system.
  • Keywords
    AC generators; photovoltaic power systems; power grids; renewable energy sources; wind power plants; Greece; RES generators; RES plants; distribution system; grid connection costs; grid operators; noninterconnected islands; photovoltaic plants; renewable energy plants; transmission system; wind power plants; grid connection cost; photovoltaic systems; renewable energy; wind energy;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    Power Generation, Transmission, Distribution and Energy Conversion (MEDPOWER 2012), 8th Mediterranean Conference on
  • Conference_Location
    Cagliari
  • Electronic_ISBN
    978-1-84919-715-1
  • Type

    conf

  • DOI
    10.1049/cp.2012.2045
  • Filename
    6521887