Title :
Construction planning simulation at GRU airport
Author :
Moretti Fioroni, Marcelo ; Franzese, Luiz Augusto G. ; Costa, Maice ; Kuhn, A.
Author_Institution :
PARAGON Decision Sci., Sao Paulo, Brazil
Abstract :
Many complex construction schedules are still being planned nowadays with deterministic project schedule tools such as MS Project, with deterministic estimates, lack of focus on event conflicts and no queuing estimates. This paper presents a discrete-event simulation approach for a soil replacement project of great importance to the Brazilian government. This was part of the expansion work at GRU Airport, the greatest and most important of the country, and was being carried by the Brazilian Army. The airport should be ready for the increasing demand expected for World Cup in 2014 and Olympics in 2016. The study started with the original deterministic schedule, and considered several external factors, like traffic, rain seasons and providers capacity. After evaluating many scenarios and identifying some bottlenecks, the best scenario was found, with a due date sooner than initially planned.
Keywords :
airports; construction industry; discrete event simulation; planning; production engineering computing; project management; scheduling; Brazilian government; GRU airport; MS Project; complex construction schedule; construction planning simulation; deterministic estimates; deterministic project schedule tool; discrete-event simulation; soil replacement project; Airports; Atmospheric modeling; Government; Rocks; Schedules; Soil;
Conference_Titel :
Simulation Conference (WSC), 2013 Winter
Conference_Location :
Washington, DC
Print_ISBN :
978-1-4799-2077-8
DOI :
10.1109/WSC.2013.6721655