DocumentCode
915622
Title
Design criteria for lightning protection of HV substations
Author
Panek, J. ; Albrecht, P.F. ; Elahi, H.
Author_Institution
GE Ind. & Power Syst., Schenectady, NY, USA
Volume
7
Issue
2
fYear
1992
fDate
4/1/1992 12:00:00 AM
Firstpage
489
Lastpage
498
Abstract
Methods that designers may use to account for substation reliability when adopting insulation coordination strategy are discussed. The choice of criteria is described in terms of the mean time between failures (MTBF). The methods for calculating the MTBF are explored considering several viewpoints: separation and limiting distances, the risk of failure and equipment lifetime, failure rate of substation and system components, substation outage effects, and system outage severity. Procedures for computation of limiting distance and MTBF, including numerical examples, are given
Keywords
failure analysis; insulation co-ordination; lightning protection; reliability; substations; HV substations; equipment lifetime; insulation coordination; lightning protection; limiting distance; mean time between failures; reliability; substation outage effects; system outage severity; Arresters; Industrial power systems; Lightning protection; Power system protection; Power system reliability; Power transformer insulation; Substation protection; Surge protection; Surges; Voltage;
fLanguage
English
Journal_Title
Power Delivery, IEEE Transactions on
Publisher
ieee
ISSN
0885-8977
Type
jour
DOI
10.1109/61.127041
Filename
127041