Abstract
Operational experiences with a 3 MW wind turbine are described in the paper, covering two years of successful operation after commissioning. The total operation time covered by the paper is 7500 h, and total power production 11 500 MWh, including operation during precommissioning tests. Availability has been 63%.
Keywords
wind turbines; 11500 MWh; 3 MW; 63% availability; 7500 h; Maglarp; Sweden; WTS-3 wind turbine;
fLanguage
English
Journal_Title
Physical Science, Measurement and Instrumentation, Management and Education - Reviews, IEE Proceedings A
Publisher
iet
ISSN
0143-702X
Type
jour
DOI
10.1049/ip-a-1.1987.0065
Filename
4647935
Link To Document