DocumentCode
991004
Title
Operating Experience with the Low-Voltage A-C. Network in Cincinnati
Author
Pinckard, F.E.
Author_Institution
Electric Distribution Dept., The Union Gas and Electric Co., Cincinnati, Ohio.
Volume
48
Issue
3
fYear
1929
fDate
7/1/1929 12:00:00 AM
Firstpage
896
Lastpage
901
Abstract
This paper describes briefly the operating experience and problems which have resulted from the installation of a four-wire, 120/208-volt secondary network system with combined light and power mains. The problems with reference to network equipment, voltage regulation, and operation of consumers´ equipment are stated with their subsequent solution. The results obtained from fifteen months operation of this system indicate that, with reasonable care in layout and selection of equipment, no operating problems of major importance will be met.
Keywords
Circuit breakers; Cities and towns; Elevators; Feeds; Graphical user interfaces; Impedance; Integrated circuit interconnections; Power cables; Power system interconnection; Voltage control;
fLanguage
English
Journal_Title
American Institute of Electrical Engineers, Transactions of the
Publisher
ieee
ISSN
0096-3860
Type
jour
DOI
10.1109/T-AIEE.1929.5055313
Filename
5055313