• DocumentCode
    991425
  • Title

    "Synchronized at the Load\´\´-III System tests and operating connections

  • Author

    Searing, H.R. ; Milne, G.R.

  • Author_Institution
    Assistant Electrical Engineer, United Electric Light & Power Company, New York, N. Y.
  • Volume
    48
  • Issue
    4
  • fYear
    1929
  • Firstpage
    1093
  • Lastpage
    1100
  • Abstract
    System test results, operating connections, and experience with the New York City system synchronized at the load are given. Data obtained by test are presented, showing the behavior of the system when generators are operated synchronized only through a low-voltage a-c. secondary network. The adaption of this method of connections to the New York City 60-cycle system, including system layout, station and feeder arrangement, and automatic recording apparatus is described. Experience with these connections has demonstrated that stable performance of prime movers is obtained, load and wattless control is simplified, oil circuit breaker duty is reduced, and voltage fluctuation at customer´s service during system disturbances is materially decreased.
  • Keywords
    Circuit testing; Cities and towns; Feeds; Impedance; Integrated circuit interconnections; Power engineering and energy; Substations; System testing; Transformers; Voltage;
  • fLanguage
    English
  • Journal_Title
    American Institute of Electrical Engineers, Transactions of the
  • Publisher
    ieee
  • ISSN
    0096-3860
  • Type

    jour

  • DOI
    10.1109/T-AIEE.1929.5055358
  • Filename
    5055358